HS2 works notification update: Parkway and Camden Cutting areas; utility surveys, trial holes and ground monitoring equipment

Parkway works update

  • The traffic management for the overnight CCTV utility surveys on Parkway on 12 to 13 April has been revised. Temporary traffic lights will be in place to manage traffic flow and Bus Stop 11996 on Gloucester Avenue will also be temporarily suspended from 8pm on 12 April to 5am on 13 April.
  • The utility trial holes on Parkway will be carried out from 9 March to 9 April, while the trial holes on Albert Street have been re-scheduled from 12 April to 10 June.
  • To view more detail and the update, please visit our work notification .
  • Camden Cutting area works update

  • Having completed the first stage of installing ground monitoring equipment on Park Village East, we have now revised the programme to complete works earlier (7 May).
  • Some of the planned CCTV utility surveys on Park Village East could not be completed due to blockages in the pipes, and have been rescheduled for the 29 and 30 March. These surveys will require temporary parking bay suspensions.
  • To view more detail and the update, please visit our work notification .
  • Posted on 25th March 2021

    by HS2 in Camden