The engagement of this project has ended
Do you want to receive an email when news items are posted?
Planned road closure - Adelaide Road:
As part of our ongoing works to set up the Adelaide Road site, we will be installing a temporary site office and welfare units at the eastern end of the Adelaide Road site on Saturday 29 May and Saturday 12 June 2021.
We will be installing sheet piles to build a retaining wall at the western end of the site. Once we have installed the sheet piles, we will move the welfare units to their permanent location at the western end of our site, next to the Adelaide Nature Reserve. We will write to you about the sheet piling works when the details are confirmed.
For further information please see our works notification.
Update: Works in the Euston Throat
For further information please see our further update notification.
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk