HS2 in Camden logoHS2 in Camden

Get project news

Do you want to receive an email when news items are posted?

News on HS2 in Camden

Back to news

HS2 works notification: UKPN weekend works in Harrington Square and Lidlington Place, 5 & 6 June 2021; Utility works in Parkway and Park Village East, 14 June to 9 July; Update of large load deliveries and collections to SCS worksite on Hampstead Road, May to June; Update of utility works on Gower St, Gower Place, Gordon St and Euston Road

UKPN will carry out trial holes in Harrington Square and Lidlington Place footway on Saturday, 5 June and Sunday, 6 June .

For further details please see our works information

UKPN cable installation on Parkway and Park Village East – 14 June to 9 July

  • Phase 1 of utility substation installation works for Euston Cavern worksite (area between Parkway and Mornington Street bridge)
  • Temporary lane and footway closures on Parkway and Park Village East
  • Access to properties will be maintained
  • For further details please see our works information

    Large load deliveries and collections – May to June

  • There will be several large load deliveries and collections via Hampstead Road or Park Village East, outside peak hours
  • For further details please our works information

    Update of utility works on Gower Street, Gower Place, Gordon Street and Euston Road.

  • The Westbound slip road of Euston Road will be reopened on 7 June.
  • Works on Gower Place and Gordon Street will be complete by 25 July.
  • For further details please our works information

    If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk

    Posted on 28th May 2021

    by HS2 in Camden