Utility surveys and works west of Euston Station

In order to determine the locations of utilities and test their condition, we need to carry out a number of trial holes (surveys) including:

  • Euston Road - 20 July until late August 2021
  • Junction of Robert Street and Hampstead Road – 6 August until late September 2021
  • Cardington Street and Hampstead Road – 16 September until late October 2021.
  • In addition, an update on our works at the former National Temperance Hospital site and at the former Maria Fidelis Catholic School is available.

    For details of these works, please see our works information.

    Event reminder - Utility surveys in the Euston Station area

    We are holding two events this week at which you will be able to:

  • Hear about how surveys help us determine the locations of utilities and to test their condition around Euston Station
  • Learn about the impacts of these surveys and how we’ll mitigate them
  • Our programme of works in the Euston Station area.
  • The events will be held from 4pm to 5pm on Wednesday 14 July 2021, and 5pm to 6pm on Thursday 15 July 2021. You can sign up for the events here.

    Posted on 13th July 2021

    by HS2 in Camden